New drain set to high not allowing water to enter drain
Reported via desktop in the Road Defect category anonymously at 08:43, Tue 28 June 2022 using FixMyStreet Pro
Sent to Bromley Council less than a minute later. FixMyStreet ref: 3629403.
The new road works outside the school are not allowing the excess water to drain away as the drains are too high in the road which is causing large puddles which during the winter will freeze and cause issues for not only the school children entering the site but also for cyclists and pedestrians alike. Riney the construction company did not take away the old surface just added material (Tarmac) and the then fitted the drain cover which explains the height of the drain.
Updates
-
Thank you for your report, this is now being investigated. Information on our services and the timeframes we aim to respond in can be found: http://www.bromley.gov.uk/ fixservices
State changed to: In progress
Posted by Bromley Council
at 08:44, Tue 28 June 2022
-
Further works are necessary to resolve the issue and have been scheduled for action.
Posted by Bromley Council
at 09:32, Wed 13 July 2022
-
Thank you for your enquiry. We can confirm that the recent resurfacing works on Lennard Road have been condemned and we are working with the contractor to get it replaced which should rectify this issue. We will provide a further update shortly on when these works will be completed.
Posted by Bromley Council
at 12:02, Mon 5 September 2022
-
We apologise for the lack of update to this enquiry we have been waiting for a programme date from our contractor when the remedial works will be carried out. Weather permitting works at this location should take place on Monday 19th December.
Posted by Bromley Council
at 10:51, Mon 14 November 2022
-
We apologise for the lack of update to this enquiry we have been waiting for a programme date from our contractor when the remedial works will be carried out. Works had been programmed before the Christmas break but due to the change in weather this was postponed, we hope to complete these works shortly.
Posted by Bromley Council
at 09:39, Monday 23 January 2023
-
We apologise for the lack of update to this enquiry we have been waiting for a programme date from our contractor when the remedial works will be carried out. The contractor is currently working on a programme and we hope to have these works completed Summer 2023.
Posted by Bromley Council
at 08:52, Monday 24 April 2023