Problems with the new bridge over Dollis Brook at Lover's Walk have been reported before. As the final tarmac layer appears not to have been laid the metal "tray" floods in rain. On Saturday 22nd August, workmen returned, but it appears all they did was drill a few holes in the sides of the "tray". As these are above the path level they won't solve anything, the bridge will still flood. Can we know when this job will be finished properly?

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Update 20/09. Nothing has been done about the bridge, although luckily there has been no rain lately so it hasn't flooded. I had an email from Capita on behalf of the council, claiming they were "aware of the problem" and were "looking for an appropriate solution". Barriers and signs indicating the bridge was closed were removed when it became obvious nothing was happening. In my reply to that email I said that no creative solution was needed, just a layer of tarmac to finish the job which began on June 15th. We now wait for floods in the Autumn rain, and a ready-made skating rink when the first frosts arrive.

    Posted anonymously at 18:03, Sunday 20 September 2020
    Still open, via questionnaire

  • Still open, via questionnaire, 18:46, Sunday 18 October 2020

Provide an update

Please note that updates are not sent to the council. Your information will only be used in accordance with our privacy policy

Next: Tell us about you

or No personal details will be stored, and you will not receive updates about this report.

Your update

Tell us about you

Do you have a FixMyStreet password?